05.26.16
The University of Minnesota’s Amundson Hall Lab Addition is a 42,000-square foot chemistry lab addition known as the Gore Annex. Remodel involved complete plumbing, HVAC, controls and fire protection services.
Sandwiched between buildings, the remodel of the 65-year-old building took place in occupied lab spaces with frequent student traffic. Lab air balancing was affected by existing building systems which required additional project team work to resolve.
Harris provided a substantial amount of value engineering ...
Read More
05.25.16
Twin Arrows Casino Resort is a five-story, 110-room, 71,630-square foot hotel addition with a 7,548-square foot spa. Harris performed installation of HVAC equipment including a 500-ton air cooled chiller and boiler, outside air and exhaust risers and a vertical and horizontal fan coil unit. Included among the plumbing installations were hot water and chilled water mechanical piping, domestic hot water re-circulation, pump, mixing valve, booster pump, water heaters and a hot water storage tank. Steel was used for mechanical ...
Read More
05.25.16
Tomson Hall was built over the top of the old science building after Regents Hall, a new science building, was constructed. The existing building was almost demolished, leaving only the foundation and columns.
Harris worked with The Boldt Company and Muska Electric to complete this design-build project on-time and under the original budget. Harris designed and installed a complete mechanical system, including plumbing, heating and cooling for this four-story building.
Six air handling units provide ...
Read More
05.25.16
The Old Music Hall now houses mathematics, statistics, computer science offices and computer labs. However, the two top floors are still used as music practice rooms.
During this 14,000-square foot renovation, all old mechanical and plumbing systems were demolished and reinstalled. Additions included a DX unit and air conditioning unit for the computer lab.
Harris eliminated the need for fin tube radiation in several locations by installing air diffusers that were located near the windows ...
Read More
04.29.16
The Radisson Hotel Bloomington is an eight-story, 400+ room hotel with an attached water park located a half-mile from the Mall of America.
Harris was contracted to provide the plumbing and HVAC services for the new hotel construction and was later awarded the mechanical scope for the water park as well. The HVAC and plumbing systems were installed floor-by-floor, starting on the ground floor. Due to the size of this job, over 5,000 sleeved penetrations were made through the ...
Read More
04.29.16
Harris was hired to take on the hydrogen compressor area in Area 4 of the Pine Bend Refinery’s new ultra-low sulfur diesel unit #29.
To accommodate the tight schedule, Harris made use of BIM modeling Flint Hills Resources provided. Harris moved two BIM/VDC drafters on-site to work with the completed model. Harris used this model to create work packages and kept productivity running at 96 percent throughout the job.
Harris installed 10,000 feet of process piping with ...
Read More
04.29.16
Harris has a long-standing relationship with the Minneapolis Institute of Art and has provided mechanical systems and maintenance work for many years. When the museum planned to build a new addition, Harris joined JE Dunn Construction to perform mechanical services for the project.
Harris’ knowledge of existing systems provided a value-add for the customer. The team was able to come in early in the planning process and devise a custom mechanical system that efficiently met the museum’...
Read More
04.29.16
Harris teamed with Von Roll Inc to provide sludge incineration at the largest of the eight sewage plants in the Metropolitan Council of Environmental Services (MCES) system. Von Roll Inc designed the incineration process. Harris helped procure the project, provided mechanical systems design and directed the construction coordination with other contractors.
The MCES project included the design, procurement and installation of three fluidized bed incinerator trains. Each train included the fluidized bed incinerator, primary and secondary heat ...
Read More
04.28.16
La Paz Regional Hospital’s new, 9,158 square foot surgical addition provides two surgical suites for major operations and two procedure suites for minor operations. The building was designed to create an open yet efficient work space, allowing patients to flow smoothly between areas while maximizing the number of people using the facility.
Harris Mechanical Southwest provided the complete plumbing and medical systems for the addition. The project required multiple shutdowns of the existing hospital’s facilities in ...
Read More
04.28.16
IKEA is a 200,000-square foot stand-alone retail space located at the Mall of America. Harris was hired by Pepper Construction’s Retail Group to provide the plumbing and HVAC for the new IKEA store. In addition to large showroom spaces designed for high visibility and flexibility, the IKEA store feature amenities not normally found in big box retail – restaurant, lounge, escalators, etc. Functional spaces included office, self-serve department, as-is department and various showrooms.
Large rooftop units fed ...
Read More