10.05.22
Harris was awarded the Malouf Mezzanine Expansion design-build project for Malouf Fine Linens. The scope of the project included turning warehouse space into a two-level mezzanine office/retail/photo area for the client. Malouf came to Harris, with the help of Big D Construction, with a design concept they wanted to execute, including a new VRF system to suit their needs for the cooler climate of their location.
Harris designed an HVAC and plumbing system that included 4...
Read More
10.04.22
The Kearns Building project was a complete remodel of the plumbing, chilled, heating and HVAC systems in the Kearns Building, built in 1911.
The remodel of the Kearns Building was done in 2 phases. First, the plumbing was removed from floors 2-10 on the west side, keeping the east side restrooms in operation. Phase 1 also consisted of removing the existing chilled water system and associated equipment and installing new duct work on the west wings and future restrooms.
Read More
10.04.22
Harris was selected by Layton Construction and Argent Group as the design-builder for the mechanical and plumbing work on the new, Innovation Pointe development. This development consists of a 40-acre master plan with 600,000-square feet of development.
The Innovation Pointe 2 project was a five-story, 141,000-square-foot office building with supporting parking structure. It was designed with the needs of today’s businesses in mind, with leading edge technology and high-end finishes.
With the modern progressive architecture ...
Read More
10.04.22
The Hill Air Force Base located in northern Utah is the sixth largest employer in the state and home of the Ogden Air Logistics Complex which manages a wide range of aircrafts. The Hill AFB Fire Crash Rescue Facility supports the base’s flight line operations and is a critical life safety facility.
Harris took a Design-Build role on the project, working closely with Colvin Engineering to design and install the plumbing, piping and HVAC systems in ...
Read More
10.04.22
Harris remodeled the HVAC and plumbing systems in a 101,000 square-foot warehouse. The space was originally a retail location and was made into a family fun/amusement center. We started underslab and cut in new plumbing for six new restrooms. The existing RTUs were retrofitted with new duct work to accommodate the new spaces. The new spaces included a laser tag area, mini golf, bowling alley and party rooms.
Several issues were resolved by our team. These included ...
Read More
10.04.22
The Williams International – Blue Phoenix Ogden Addition project was a new manufacturing plant for Williams International in Ogden, Utah. This was a fast-paced project where the mechanical and plumbing design was happening while the shell of the building was going up. From design initiation to completion, the total duration was 8 months. This included the design of a highly efficient process cooling system that incorporated four fluid coolers, four air handlers, and three water cooled chillers. This project ...
Read More
10.03.22
Miracle Mile Shops is a 1.2-mile-long shopping mall on the Las Vegas Strip. It consists of 170 stores, 15 restaurants and live entertainment venues. Miracle Mile Shops decided to add their own Central Plant due to energy rates from a Centralized Utility Plant (Westgate) that they are currently attached to. They added (3) 1,000-ton York YMC2 Chillers as well as (3) B&G Chilled and Condenser Pumps and (3) Marley Cooling towers, along with a piping system to serve their (3) main Energy Transfer ...
Read More
10.03.22
Harris is once again involved in constructing the latest iconic location on the Las Vegas Strip. Once completed in 2023, MSG Sphere will be a state-of-the-art 20,000 seat concert and special event venue that will provide an amazing once-in-a-lifetime visual and auditory experience. The MSG Sphere will have 170,000 sq. ft. of interior ultra HD LED screens and all sound will be delivered by “beamforming” technology, instead of overhead hanging speakers, allowing all attendees to experience any event the exact same way ...
Read More
10.03.22
For over 30 years, Harris has been the HVAC contractor of choice for Verizon Communications, a large communications and data provider based out of Basking Ridge, NJ. We received our master subcontractor agreement with Verizon in 1990. In preparation for the rollout of the nationwide 5G wireless network, Verizon has made tremendous investments to update their existing data centers to facilitate the new servers needed to implement this new technology. They own over 600 switching sites and data centers in the DMV ...
Read More
10.03.22
The Pepco Waterfront Substation project was a new substation installation for the Potomac Electric Power Company of Washington, D.C. It was a design-assist job with Coakley Williams Construction and their mechanical engineer, META Engineers. The building had to be designed to house and accommodate a new ABB turbine technology that Pepco was using to make power with a smaller footprint than their traditional power plants. The site in Southeast Washington, D.C. was selected because of its proximity ...
Read More